Progress Measurement with Hatch Engineering
During the construction of the Ravensthorpe Nickel Mine GMi was commissioned to develop a progress measurement tool for monitoring pipe work installation.

As the project had been running for well over a year there was an extreme urgency to get the system running and populated with data ASAP. GMi were able to deliver a system within four weeks and was reporting progress to the end of the project.

GMi have now expanded the system to incorporate all major commodities including earthworks, concrete, structural steel, cabling, C&I, piping, tanks, mechanical and electrical equipment.